Print Back to Calendar Return
    21.    
City Council Regular
Meeting Date: 09/10/2019  

SUBJECT:
PINE AVENUE BETWEEN STATE ROUTE 71 AND BUTTERFIELD RANCH ROAD - PAVEMENT REHABILITATION PROJECT
RECOMMENDATION:
  1. Adopt a Resolution entitled: A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF CHINO HILLS, CALIFORNIA, APPROVING THE DESIGN AND PLANS FOR CONSTRUCTION OF THE PINE AVENUE PAVEMENT REHABILITATION PROJECT PURSUANT TO GOVERNMENT CODE SECTION § 830.6.
     
  2. Authorize staff to solicit bids for construction. 
     
  3. Determine the project to be exempt from review under California Environmental Quality Act of 1970, as amended, Public Resources Code Section 21000 et seq. (“CEQA”) pursuant to Section 15301 of CEQA Guidelines.
BACKGROUND/ANALYSIS:
The Pine Avenue Pavement Rehabilitation Project (“project”), between State Route 71 and Butterfield Ranch Road (Exhibit A), is included as a part of the approved FY 2019-20 Capital Improvement Program (CIP). Staff has completed the construction plans and specifications for the project. The work includes full-width pavement asphalt grind and overlay, restoration of striping, installation of video detection at the intersection of Pine Avenue and Butterfield Ranch Road, and pavement legends and markers.
 
Staff is requesting approval of the plans and specifications for this project as well as authorization to advertise the project for construction. The engineer’s cost estimate for the project is $420,000 including the design, construction contract, contract administration, and 10% for contingencies.
ENVIRONMENTAL (CEQA) REVIEW:
The project has been determined to be exempt as a Class 1(c) Categorical Exemption (existing highways and streets, sidewalks, gutters, bicycle and pedestrian trails and similar facilities), pursuant to Section 15301 of Guidelines for the California Environmental Quality Act of 1970, as amended, Public Resources Code Section 21000 et seq.
FISCAL IMPACT:
The current Capital Improvement Program has $420,000 budgeted for the Pine Avenue Pavement Rehabilitation Project. There is no anticipated impact on the General Fund with this item. 
 
REVIEWED BY OTHERS:
This item has been reviewed by the Finance Director.