On September 24, 2024, the City Council approved the plans and specifications for the City Yard Exterior Staff Restroom Addition Project and authorized staff to solicit bids.
The project is comprised of the installation of a prefabricated restroom adjacent to an existing storage building located at the City Yard. The project also includes the construction of a concrete pad, the reconstruction of asphalt pavement around the proposed concrete pad, and the completion of necessary improvements for the connection of water and sewer for the restroom.
On October 24, 2024, two bids were received and are summarized as follows:
Contractor |
Bid Amount |
Golden Coast Construction |
$ 400,166.95 |
Corner Keystone Construction Corporation |
$ 488,820.00 |
Golden Coast Construction was announced as the apparent low bidder at the bid opening. The licensing and bonding information included in their bid has been reviewed and meets the minimum requirements. Therefore, staff recommends that the City Council award a contract in the amount of $400,166.95 to Golden Coast Construction.
|